Bavaria Tower marks one year of operation

20.07.2017

These works started in April 2016, and are made of two towers, Tower B and C, which rise above ground floor. The founding slab (general depletion) was concluded in middle August/ September and the ground floors were concluded in October/ November. Tower C will have its structure finished by the end of June 2017 and Tower B in October 2017.